A 360 Closure: 2 April - [13] July 2024
Schedule of works
Work is scheduled to begin on 2nd April and the temporary closure will be in place until mid-July. Scottish and Southern Electricity Networks (SSEN), working on behalf of National Highways, will be installing high voltage and fibre optic cabling along the route to support the A303 Stonehenge project. Work will be carried out in one lane of the road, with machinery and equipment positioned in the other lane.
Access to homes and businesses
While this stretch of the A360 will be closed completely to through traffic, access to homes, businesses and for emergency services will be maintained. We have already reached out to the nearest residents and businesses to the closure and will continue to work with them, and the wider community.
Contacting the project team
Once work is underway, the closure will be staffed between 7am and 7pm each day and security will be on site 24 hours a day. The team on site will be happy to help if you have any queries or need to request special access for a large vehicle, for example.
Ahead of work beginning and throughout the project, you can contact the team by phone or email. The project website will be kept up to date with information about the work and you can also sign up for email updates through the website.
Email: info@a360temporaryclosure.co.uk
Tel: 03301 755 675
Website: a360temporaryclosure.co.uk
Parish Council Meeting:
Mon 1 July 2024.Draft Minutes
Next Meeting: Mon 4th November 2024: Agenda to follow
200 Club: July & August 2024 Winners
Updated Village Events are all now in the Village Calendar
Village Hall News UPDATED 6th October 2024
Now lapsed
Valley Art; details
REGULAR ITEMS
October 2024 meeting report; date of next meeting: 7th November 2024